Satellite and drone images reveal big delays in US data center construction

TechnologyApril 17, 2026
2 min read
Satellite and drone images reveal big delays in US data center construction
Data centers face construction delays and energy bottleneck as resistance grows.
Reading Settings

Silicon Valley has been pouring hundreds of billions of dollars into building ever-larger AI data centers that require as much electricity as hundreds of thousands of US homes—but that massive buildout faces significant construction and power challenges along with growing local resistance. Now satellite imagery is showing that nearly 40 percent of US data center projects may fail to be completed this year as scheduled.

The Financial Times drew upon satellite imagery from the geospatial data analytics company SynMax showing how much progress has been made in clearing land and laying building foundations for each data center project. It also cross-checked project progress against public statements and permit documents compiled by the industry research group IIR Energy. The resulting analysis revealed how major projects from tech companies such as Microsoft, Oracle, and OpenAI are “likely to miss completion dates by more than three months.”

Interviews with more than a dozen industry executives highlighted data center delays caused by “chronic shortages of labor, power and equipment” along with the process of securing the necessary permits, according to the Financial Times. Construction executives involved with OpenAI projects specifically mentioned not having enough tradespeople, such as electricians and pipe fitters, to work on multiple data center projects.

Read full article

Comments

Source: Ars Technica

Share this article

Related Articles

The $400 million machine powering the future of chipmaking
Jun 2358 minutes ago

The $400 million machine powering the future of chipmaking

Jos Benschop is climbing a ladder to get to the top of his newest machine.  It’s a bit of a schlep. The contraption is the size of a double-decker bus—more than 150 tons of gleaming precision-mil

technologyreview.com27 min read
Read More
Elephant alert! AI warning systems aim to avoid deadly clashes
Jun 2358 minutes ago

Elephant alert! AI warning systems aim to avoid deadly clashes

India is home to about 60% of the world’s wild Asian elephants, and around 80% of the animals’ habitat lies outside protected areas, according to the Ministry of Environment, Forest, and Climate Chang

technologyreview.com2 min read
Read More